Project Scope
 
 Completion: 2014

 

Considered systems: Complete CIP Structure, Hybrid between CIP or Total Precast


Square Footage: 392,902 SF


Total Pieces: 2973

Products: Beams, Raker Beams, Columns, Walls, Spandrels, Moment Frames, Double Tees, Flat Slabs, Stairs, Landings, Stadium Seats.


Benefits: Speed of construction, cost effective, reduced site disturbance, and less trades/coordination. 

Owner: City of Orlando

Architect: HNTB Corporation

Engineer: Walter P. Moore & Associates, Inc.

Contractor: Turner Construction Company